What does a will-serve letter establish for diligence?
Only the commitments and conditions in that particular document. Verify its site, customer, MW, dates, validity, and relationship to the governing service agreements.
Power diligence guide
Power due diligence should establish which capacity is supported by current documents, which conditions remain open, and what must happen before initial and full-load energization. Use a versioned document request and risk register to test the MW, dates, costs, rights, and obligations before relying on the power claim in a transaction.

| Document set | What to verify |
|---|---|
| Utility letters and agreements | Current issuer response, parcel and customer, MW, validity, reservation, conditions, service class, and assignment. |
| Load letter and commissioning/ramp plan | Utility demand versus IT demand, initial and ultimate phases, operating profile, and consistency across documents. |
| Study package | Latest reports and appendices, assumptions, version history, limitations, upgrades, and open technical issues. |
| Cost and security record | Upgrade scope, estimate basis, allocation, payment evidence, security, refundability, and remaining obligations. |
| Schedule and rights | Critical path, responsible parties, easements, permits, equipment, construction, testing, and required approvals. |
| Correspondence and changes | Written clarifications, changed assumptions, exceptions, outstanding questions, and the date each conclusion was reconfirmed. |
Where on-site generation is part of the plan, add fuel, equipment, operating limitations, and environmental authorizations. A backup-power assumption does not replace diligence on the intended operating mode.
Flag a letter for another parcel, inconsistent MW or ramp figures, missing study appendices, expired conditions, an unfunded upgrade, or a service date unsupported by equipment and construction evidence. Keep the finding open until the responsible party supplies the missing document or the decision explicitly accepts the risk.
Read the will-serve letter checklist and dated timeline guide. The network upgrades and system impact study definitions provide useful reference points. Volterra’s Transaction Support connects the diligence record to the specific transaction and its decision gates.
Only the commitments and conditions in that particular document. Verify its site, customer, MW, dates, validity, and relationship to the governing service agreements.
No. Check required agreements, upgrades, funding, permits, rights, equipment, testing, and energization approvals in addition to the study results.
Identify the estimate’s scope, date, exclusions, allocation, and uncertainty. Separate it from amounts already committed or paid and quantify the remaining exposure.
A dated service plan that matches phased MW and conditions, with identifiable work, responsible parties, equipment, permits, and approvals supporting the critical path.
Refresh it before a material commitment and after a significant change to load, site, customer, design, studies, costs, or schedule. Keep prior versions so the decision remains traceable.