Who should receive the first capacity request?
Start with the electric utility serving the actual parcel. Confirm how its transmission owner and regional operator participate in the applicable load-service process.
Power diligence guide
Submit a site-specific load request to the serving utility and obtain a written, phased service plan supported by the applicable studies and agreements. Establish the MW available at each phase, the conditions and upgrades behind each date, and who is responsible for completing them.

| Region | Process to confirm | Timing evidence to obtain |
|---|---|---|
| PJM territory | The serving utility and transmission owner’s load-service route, with applicable PJM planning and current large-load requirements. | Written utility/owner milestones for studies, upgrades, and phased service. PJM generation-queue durations are not retail energization dates. |
| ERCOT | The interconnecting TSP/DSP’s current large-load route and applicable ERCOT eligibility, documentation, and study requirements. | Project-specific study and energization milestones. Check active requirements; do not reuse deadlines from a closed Batch Zero window. |
| Other regions | The serving utility’s process and the relevant transmission provider or grid operator’s requirements. | A dated scope, study sequence, cost responsibilities, and initial/full-load schedule for this site. |
No universal PJM, ERCOT, or national interval establishes when a particular site will energize. A study target, a forecast entry, and construction completion are different milestones.
Investigate a single undated MW claim, a date without named upgrades, an unexplained mix of IT and utility MW, or a seller using a generator queue number as proof of load service. Use the will-serve checklist and system impact study definition to identify the missing evidence.
Dominion describes phased service and infrastructure dependencies. RMI separately explains the scope and limits of load interconnection studies. The following official process pages should be rechecked at the next decision point.
Start with the electric utility serving the actual parcel. Confirm how its transmission owner and regional operator participate in the applicable load-service process.
No. The load letter describes the customer’s requested demand and operating assumptions. Obtain the utility’s separate written response and the supporting service documents.
No. A generation interconnection request and a customer load-service request have different rights, studies, and dependencies. Confirm the process governing the proposed site.
Yes. Record the MW and conditions for commissioning, each subsequent phase, and full load so the development schedule does not assume capacity arrives all at once.
Record the unresolved studies and dependencies, identify the next decision milestone, and compare a smaller initial load, a different ramp, or another site.